Phase 3 – Construction
(in process of obtaining funds)
3A – Archaeological Survey (cost estimate = $74,700)
Phase 1 is required by PHMC
Phase 2 if cultural materials are found in Phase 1
3B - Lock 31 House Restoration (cost estimate = $614,700)
Urgent needs (cost = $108,000):
Fire/security detection system
Upgrade telephone & electrical services
Repair failing areas of stone foundation & wood sill on S & W sides
Short-Term needs (cost estimate = $247,700):
New slate shingle roof & chimney reconstruction
Repairs to windows, shutters, & doors
Reconstruct porches & repaint exterior
Long-Term needs (cost estimate = $279,000):
Wallpaper treatment by conservator
Structurally upgrade 1st & 2nd floor framing & new second stair
Electrical upgrade
Repair of wooden elements (interior doors, etc.)
Interior replastering & painting